Process
The website upgrades phase will follow that same process as the past:
- [We] will Create D11 feature branch
- [You] will have 2 weeks to Identify and fix any issues, then once you let me know
- [We] Merge D11 website to become LIVE
The whole process will be communicated and tracked via a service desk ticket
Upgrade Schedule
At this stage the plan is:
| 2026 Dates | Schedule |
|---|---|
| 4 Feb -18 Feb | Group 1 |
| 11 Feb– 25 Feb | Group 2 |
| 18 Feb– 4 Mar | Group 3 |
| 25 Feb – 11 Mar | Group 4 |
| 4 Mar– 18 Mar | Group 5 |
| 11 Mar– 25 Mar | Group 6 |
| 18 Mar– 1 Apr | Group 7 |
| 25 Mar– 8 Apr | Group 8 |
| 1 Apr– 15 Apr | Group 9 |
| 8 Apr– 22 Apr | Group 10 |
| 15 Apr– 29 Apr | Group 11 |
| 22 Apr– 6 May | Group 12 |