Drupal 11 Process and Upgrade Schedule

Process

The website upgrades phase will follow that same process as the past:

  1. [We] will Create D11 feature branch
  2. [You] will have 2 weeks to Identify and fix any issues, then once you let me know
  3. [We] Merge D11 website to become LIVE 

The whole process will be communicated and tracked via a service desk ticket

Upgrade Schedule

At this stage the plan is:

2026 Dates Schedule
4 Feb -18 Feb Group 1
11 Feb– 25 Feb Group 2
18 Feb– 4 Mar Group 3
25 Feb – 11 Mar Group 4
4 Mar– 18 Mar Group 5
11 Mar– 25 Mar Group 6
18 Mar– 1 Apr Group 7
25 Mar– 8 Apr Group 8
1 Apr– 15 Apr Group 9
8 Apr– 22 Apr Group 10
15 Apr– 29 Apr Group 11
22 Apr– 6 May Group 12

❗ Drupal 10 will reach end of life June 2026